Installation of over 400 large diameter helical piles to support natural gas modular piping from the on-site natural gas power plant. The project was awarded and the following week, USH load testing team mobilized to conduct axial and lateral load testing confirming the pile design. Production piles were installed 3 weeks later, staying ahead of the modular skid piping as they were set directly on top of the helical piles.
Details
Project Size: 1 GW Energy Storage
Pile Quantity: 400
Location
Claude, TX
Project Type
Data Center
HAVE A SIMILAR PROJECT?
Our team specializes in Data Center foundation packages